PMP?每日一練試題內(nèi)容(2023/3/16)
試題1
During a project's next phase,an architect will take a three-month maternity leave.What should the project manager evaluate to determine if this is a risk,issue,or opportunity查看答案
試題參考答案:B
試題解析與討論:m.ichunya.com/st/478271917.html
試題2
A company was acquired by a big company that wanted to focus on its core products and services.The projects in the planning phase are being revised to include the new change management process. The project manager of a project needs continuous high-level input to ensure consistency with the new organizational structure. What should the project manager do to ensure that project changes are managed effectively?A. Reopen the requirements, expand the project to include the new change management process, and designate a team member to take full respons1bility for change management. B.Determine which change controls apply to the project, implement only those relevant and查看答案
試題參考答案:D
試題解析與討論:m.ichunya.com/st/4840714983.html
試題3
A project manager suspects there is a quality defect in a recently produced batch of products. However, a test for this defect will be destructive to the products. What should the company do next?查看答案
試題參考答案:C
試題解析與討論:m.ichunya.com/st/49600147.html
試題4
項目經(jīng)理建立了一個虛擬團隊,盡量減少項目成本,然而,經(jīng)過幾個月緩慢進展和成本超支后,項目發(fā)起人開始抱怨,項目經(jīng)理應該怎么做?查看答案
試題參考答案:C
試題解析與討論:m.ichunya.com/st/4619613665.html
試題5
你正在管理一個通過采購開發(fā)軟件產(chǎn)品的項目。項目團隊跨越3個國家,5個時區(qū),同時因為項目規(guī)模的原因,你對成本感到很擔心。下列哪種類型的合同能降低成本?查看答案
試題參考答案:C
試題解析與討論:m.ichunya.com/st/4752410430.html
試題6
在查看項目進度的圖表表示時,項目經(jīng)理看到一個周期性跨越上下基準數(shù)字的參數(shù),項目經(jīng)理正在查看哪一項?查看答案
試題參考答案:A
試題解析與討論:m.ichunya.com/st/4651329916.html
試題7
哪個是對質(zhì)量審計正確的描述:查看答案
試題參考答案:C
試題解析與討論:m.ichunya.com/st/425785069.html
試題8
You have always been asked by your management to cut your project estimate by ten percent after you have given it to them.The scope of your new project is unclear and there are over 30 stakeholders. Management expects a 25 percent reduction in downtime as a result of the project. Which of the foll owing is the BEST course of action in this situation?查看答案
試題參考答案:C
試題解析與討論:m.ichunya.com/st/489909723.html
試題9
項目經(jīng)理完成了項目章程。項目經(jīng)理下一步必須執(zhí)行什么?查看答案
試題參考答案:D
試題解析與討論:m.ichunya.com/st/472749867.html
試題10
During a monthly project status meeting, the project manager learns that the local government announced funding that could affect the Project. What should the project manager do next?查看答案
試題參考答案:B
試題解析與討論:m.ichunya.com/st/492088023.html
信管網(wǎng)訂閱號
信管網(wǎng)視頻號
信管網(wǎng)抖音號
溫馨提示:因考試政策、內(nèi)容不斷變化與調(diào)整,信管網(wǎng)網(wǎng)站提供的以上信息僅供參考,如有異議,請以權威部門公布的內(nèi)容為準!
信管網(wǎng)致力于為廣大信管從業(yè)人員、愛好者、大學生提供專業(yè)、高質(zhì)量的課程和服務,解決其考試證書、技能提升和就業(yè)的需求。
信管網(wǎng)軟考課程由信管網(wǎng)依托10年專業(yè)軟考教研傾力打造,教材和資料參編作者和資深講師坐鎮(zhèn),通過深研歷年考試出題規(guī)律與考試大綱,深挖核心知識與高頻考點,為學員考試保駕護航。面授、直播&錄播,多種班型靈活學習,滿足不同學員考證需求,降低課程學習難度,使學習效果事半功倍。
發(fā)表評論 查看完整評論 | |