When reviewing a project where quality is a major concern, an IS auditor should use the project management triangle to explain that: 
A、increases in quality can be achieved, even if resource allocation is decreased. 
B、increases in quality are only achieved if resource allocation is increased. 
C、decreases in delivery time can be achieved, even if resource allocation is decreased. 
D、decreases in delivery time can only be achieved if quality is decreased. 